How many battery projects in New York's interconnection queue get built?
Every New York utility files a monthly inventory with the state of the projects applying to connect to its distribution grid. In the October 2026 editions, covering seven utilities, 4,036 battery projects over 2 MW had applied since the end of 2015. Seventy-six were complete. 2,891 had been withdrawn. The other 1,069 were still in the queue.
So a feeder near your site with a long list of queued batteries usually has a much shorter list of batteries that will get built. Here's how to tell the two apart.
About 38 withdrawals for every battery that connected
For a large filing, withdrawal is the usual ending. Seven in ten large battery filings ended that way, and four in five large solar filings. Small systems are a different queue: under 500 kW, fewer than one in ten of either was withdrawn.
The active queue holds about 5,900 MW of large batteries. The ones that have connected add up to about 430 MW.
The newest filings look healthier than they are
Sorted by the year they applied, 84% of 2023's large battery filings had been withdrawn by October, 79% of 2024's, 76% of 2025's and 43% of 2026's. That isn't a sign the projects got better. A filing from this spring hasn't had time to reach the point where most are dropped.
Volume jumped at the same time: 558 large battery filings in 2024, 1,189 in 2025, and 894 so far in 2026. Most of today's active queue is young, and young is when a filing is least likely to last.
Most leave before the study comes back
Projects this size usually go through a detailed study, the CESIR, which prices any upgrades the utility needs to make. Six in ten of the withdrawn battery filings had no finished CESIR on record. Their developers left before the utility had priced the connection.
For the rest, the price was often the problem. Under New York's rules the developer pays for upgrades in cash, up front, often years before the utility spends the money. At the three upstate New York utilities in the data, the median estimate on withdrawn projects with a finished study was about $250 per kW, and one in four was above $1,400 per kW. On the projects that connected, the median was under $70.
The bill can also move after the study. In August the Public Service Commission declined to cap final upgrade costs at 115% of the estimate. From March 2027, utilities have to publish how their estimates compared with what the upgrades actually cost.
Not every withdrawal is about the grid. The same order found that projects taking 2.75 to 4.5 years to finish were held up mostly by local permits, financing and equipment, not by the utility's study.
A withdrawal isn't always the end of the site
About three in ten withdrawn large battery filings were followed by another application from the same developer on the same circuit, usually within three months. Developers withdraw and refile to change the size, move the connection point, or start again under new rules. The same site can show up in the inventory more than once, so count sites, not rows.
The filings worth planning around
Withdrawn rows stay in the inventory, so start by counting active filings, not all of them. Among the active ones, about half have a finished CESIR and a priced upgrade. Those are the projects most likely to be built.
If you're adding load, a queued battery is also load when it charges, on the same feeder (charging vs discharging headroom). If you're developing, the filings ahead of you that matter are the same ones; most of the rest will drop out.
None of this is quick to do by hand. A single utility's inventory can run past 100,000 rows, a refiled project appears as several of them, and the circuit IDs aren't always written the way the capacity map names its feeders: for about three in ten circuits with an active large battery filing, the two didn't match exactly. And the map shows only today's headroom, not how much it has moved since the projects ahead of you filed (reading the fine print on a utility capacity map). For how the queue's review tracks work, see distribution interconnection queues.
If you'd like the queue near a site read for you, send an address. We'll match the filings to the feeders that serve it, set aside the withdrawn and duplicate rows, show which active projects have finished their study and priced their upgrades, and set that against how those feeders' published capacity has changed.