What one refresh did to Central Hudson's map
From my first capture on February 25 until April 8, 2026, Central Hudson's capacity map carried figures dated May 2025. By April 15 it had refreshed with figures dated March 2026. Of the 217 feeders I could match before and after, all 217 changed: 174 went down and 43 went up. Another 30 feeders dropped off the map. Anyone who checked a site before April was working from numbers that had since moved.
See the full Central Hudson finding →
- Feb 25, 2026: First capture. Figures dated May 2025.
- Apr 15, 2026: Refresh. All 217 matched feeders changed.
- Nov 19, 2026: 37 weeks archived so far.
Summer load-serving headroom, Central Hudson Gas & Electric. Counts from my own archive. Not affiliated with or endorsed by Central Hudson.
Why not just check the utility's map?
The map shows today. This shows what changed.
Every reading is kept with the date the utility gives and the date it was archived, so you can see when a figure moved.
Each utility measures something different.
Load-serving headroom, EV hosting capacity and electrification headroom are labeled and never mixed, so you know what a number means before you quote on it.
Neighboring utilities in one place.
Records near a site are searched across the utilities covered, which helps when the serving utility isn't obvious.
The right question for the utility.
Each answer ends with the specific question that gets a useful reply from the utility, which still confirms serving equipment and cost.
What you get
One site, free.
A one-page written answer within 2 business days: the published capacity near the site, whether it changed, and what to ask the utility. See an example →
A list of sites.
Up to ten addresses in one brief. See an example brief →
Site watch.
An email when the published capacity near your sites changes.
Tools and API.
Full values and history in site search, batch screening, demand scenarios and the API. See the tools →
Working for a client? Any check or brief can be delivered white label, under your firm's name.
Prices for more sites and for monitoring are on the Prices page.
Why a published figure needs a second look
How a published figure can mislead
Illustrative example. Bank names and values are synthetic and do not come from any utility’s files.
| What the utility's file says | What the research finds | Question for the utility |
|---|---|---|
| The utility’s February file lists 48.0 MW of headroom at Bank A, the bank nearest the site. | In the files, February’s peak is zero, so the headroom equals the bank’s full rating. March shows a positive peak and 30.5 MW of headroom. The files do not explain the zero peak or why the peak entries differ. | What does a zero peak mean, and does this bank serve the site? |
The utility still needs to confirm which equipment serves the property.
Coverage: most of Rhode Island and Washington, DC, and parts of New York, New Jersey, Connecticut, Maryland, Delaware, Maine and California. Coverage varies by utility; see data quality and corrections. Utility confirmation is needed for serving equipment, connection route and project requirements.
Recent writing
- What a public map can and cannot answer before you ask
What published capacity maps can support in site screening, and what requires a project-specific utility answer.
- What a building’s electrical service rating tells you
Amps, voltage and phase describe the existing service. They do not establish spare capacity in the building or additional capacity on the utility network.
- Who pays for the line
What New York's service rule and the utilities' published pages say about cost responsibility for extending service to a new load, with Maine's schedule as a worked example.
Who's behind this
I'm Ash Wang, and I used to cover EV charging as an analyst at Bloomberg. Now I archive utility capacity maps every week and write up what they show for people placing new load.