Distribution interconnection queues
How distribution interconnection backlog differs from transmission-level
By the time a federal appeals court upheld FERC's big interconnection reform, interconnection queues held roughly 2,600 gigawatts of proposed generation and storage capacity at the end of 2023, and even after two years of reform, the queues were still sitting above 2,060 gigawatts by the end of 2025. There was more capacity waiting to connect than the country currently has installed. That's the backlog most people have heard about, the one that got FERC to replace its old first-come-first-served review with a mandatory first-ready, first-served cluster study process under Order No. 2023.
That backlog is at the transmission level, under FERC's jurisdiction, and it's almost fully large generation and storage projects trying to connect to the bulk power grid. These interconnection requests are studied by an ISO or a transmission-owning utility because it could affect grid stability across a wide region.
Distribution-level interconnection is very different and less publicized. It’s governed by state commissions rather than FERC, and it runs on rules that mostly trace back to a much older FERC action: Order No. 2006, from 2005, which gave states a model set of small-generator interconnection procedures to adapt rather than mandating one national process. That's why interconnection rules look different from state to state. Utah, Virginia, and others made their own three tier structures for systems up to 20 megawatts off that starting template, each with its own specific thresholds and screens.
New York's own Standardized Interconnection Requirements, the SIR, cover generation and storage of 5 MW or less and set out two application tracks.
- Systems of 50 kW or less follow the shorter set of steps. Certified inverter-based systems up to 300 kW can use it too.
- Systems above 50 kW and up to 5 MW follow a longer process. The utility runs preliminary technical screens first, and supplemental screens can follow.
- A project that the screens do not clear goes to a full study, which New York calls a CESIR: a Coordinated Electric System Interconnection Review.
The CESIR is one review, not the feasibility, system impact and facilities sequence used for transmission. It looks at the project's effect on the utility system and at whether the design meets the SIR's requirements. The SIR sets a deadline in business days for each step, and the Commission has revised the document several times since 2025, so check the current edition on the Department of Public Service's distributed generation page before relying on a deadline.
Unlike transmission requests, these applications don't get batched into an annual cluster. Distribution projects are still generally reviewed one at a time, in the order they arrive, because a solar array's impact on one distribution circuit typically doesn't depend on what's happening three circuits over the way large transmission connected projects can share the same upstream network upgrade.
That makes distribution-level queues backlogs look local rather than nationwide. A 2016 South Carolina Public Service Commission order dealing with Duke Energy's interconnection process is an example. The state's Office of Regulatory Staff had documented a processing backlog and pushed for utility-specific remedies, such as an Interdependent Project Review Process for handling multiple pending projects on the same circuit and a mandated 10% cut to the completion time for system impact studies. California's Rule 21 process has its separate performance record as well. Tracked data on Rule 21 timelines has shown some process steps completed on schedule in under half of cases, a compliance problem addressed through state rulemaking rather than any federal order.
A headline about gigawatts stuck for years is a transmission queue that is affected by cluster studies and network upgrade cost allocation among generators that share the same upstream constraint. A distribution level application for a new load or a smaller DER project is answering a more local question, decided by a state commission's own tiered screening rules, and its timeline depends more on which track the project lands in and the circuit.