Charging vs discharging headroom on a battery storage capacity map
In a January 14, 2026 notice to New York regulators, Con Edison said about 2,500 MW of battery storage was in its distribution interconnection queue, against about 115 MW in operation at the end of 2025. Sixty-five percent of the queued megawatts connect through 10 of its 63 substations, and more than 20 substations were at or near their hosting capacity limits. The problem it described was not export. It was charging: enough batteries filling up overnight in one area could create a new overnight peak larger than the area's daytime peak.
That is why a storage capacity map gives two numbers for every circuit, and why the smaller one usually decides the site.
One feeder, two layers
New York's utilities each publish a battery storage hosting capacity map with two layers, and you have to switch between them. The charging layer treats the battery as load. It shows how much more draw the circuit can take before it overheats a conductor or lets voltage sag too low. The discharging layer treats the battery as generation. It shows how much export the circuit can take before voltage rises too high, a conductor overloads, the lights flicker, or the utility's protection, including anti-islanding, runs out of room.
The two layers are tested at different times. The Joint Utilities describe the charging run as starting from the feeder's summer peak and the discharging run from its minimum daytime load, the same condition the solar map uses. So the two numbers on one feeder can be far apart, and neither is "the" capacity of the site. In one Joint Utilities training example, a feeder showed 800 to 1,200 kW for charging and 200 to 600 kW for discharging.
Size the battery against the smaller layer
A 2 MW, 8 MWh battery can charge at 2 MW and discharge at 2 MW. Both layers have to clear it unless one direction is limited. Compare the inverter rating in MW, not the energy rating in MWh, with the minimum value each layer shows for the feeder that serves the site. If you're unsure of the units, check them first. (When an MVA label does not mean you should convert to MW.)
If one direction comes up short, that tells you what to ask the utility about: an export limit when discharging is the problem, a charging limit or schedule when charging is. The map doesn't say what the utility will accept. The interconnection review does.
Check where the values apply, too. Central Hudson, for example, publishes storage values only for the three-phase mainline of each feeder, and only for systems of 300 kW and up. A single-phase lateral by the lot has no storage number at all. (Single-phase, two-phase and three-phase feeders.)
Read the hours the map assumed
Central Hudson and Con Edison both say their storage analysis assumes the battery operates between 10 a.m. and 8 p.m. Many batteries are planned to charge overnight and discharge in the late afternoon. That is a different schedule from the one the map tested.
Con Edison's notice is about exactly that gap. Overnight load is low, so overnight charging looks like spare room, until enough batteries charge in the same hours. Its procedures already say that charging during a network's peak period needs extra engineering review. Since October 2025 it has also asked two questions of each project: does its charging create a new peak at the area substation or on the sub-transmission system, and does it push past a 70% reliability threshold? Upgrades are required only if the answer to both is yes.
This test is disputed. Storage industry groups, including NYSEIA and NY-BEST, have asked the Public Service Commission to stop Con Edison from using it, and Con Edison has asked the Commission to deny those requests. If a site depends on it, check where the case stands before you price the project.
This spring, some New York utilities added schedule-based storage values to their maps, which reflect approved charging and discharging schedules. If your utility's map has them, read the one closest to how your battery will actually run.
Don't use the EV map as the battery's charging number
The charging layer and the EV (electrification) map both describe load, but they're built differently. The Joint Utilities describe the electrification map as simple headroom: the equipment rating minus the historical peak, thermal limits only. The charging layer comes from a power-flow model that also checks voltage. The two won't match, and they aren't meant to. For a battery, use the charging layer. (Hosting capacity maps vs distribution load serving capacity maps.)
Look above the feeder
Con Edison's constraint sits at the area substation and the sub-transmission system, not only on the feeder. A circuit can show room on its own while the station behind it is full. Con Edison marks constrained areas red on its map and said it would mark areas where overnight charging room is shrinking differently. Read the substation fields in the pop-up, not just the feeder color.
Write down the date of both numbers
Storage values are recalculated on a study cycle. Con Edison refreshes its solar and storage hosting capacity every April, and Central Hudson recalculates its storage map each April 1, with an October 1 update for circuits that picked up 500 kW or more of new DER. Connected and queued DER fields usually change monthly. The Joint Utilities also say queued DER is typically left out of the storage calculation, which matters most where the queue is long. (How often utilities refresh their capacity maps.)
Know what the map is
Every utility says the same thing: these are screening values, not an interconnection approval, and they don't replace the utility's engineering review. In New York, that review is the CESIR. A zero on either layer means the model found a limit under its assumptions, not that a project is impossible.
If you want a second look at one site, send an address. We'll tell you what both layers show near it and what to ask the utility.