Reading the fine print on a utility capacity map
Click a feeder on a utility capacity map and the number everyone reads is the headroom. Around it sit a dozen other fields: dates, ratings, a substation line, queued generation, sometimes a box marked Notes. On Central Hudson's storage map this November, 101 of its 244 feeders carried a note, and on 73 of the 230 with a charging figure, a voltage test set the number or tied with the thermal limit. Central Hudson's load map, the one most charger contractors open first, has no notes field and doesn't test voltage at all.
Those other fields are where a utility tells you when the headroom doesn't mean what it seems to. Here's how to read them.
One map can carry three dates
A pop-up usually dates the capacity study and, separately, the last count of connected and queued generation. They run on different clocks. In November, Central Hudson's load figures were dated March 31, 2026. Its storage map dated most of its capacity figures April 1, a small share of sections September 1, and its generation counts October 30.
The study date is the one that goes with the headroom. Copy it into your notes, not the date on the page, and check whether the section near your site carries a later date than the rest. (How often utilities refresh their capacity maps.)
Find out which limit set the number
On solar and storage maps, the figure is the lowest of several tests. Central Hudson's storage map runs four for charging: primary undervoltage, primary voltage deviation, regulator deviation and thermal. In November the thermal test set the charging figure on its own on 157 of 230 feeders. On the other 73, a voltage test set it or tied, mostly undervoltage.
The kind of limit tells you how much the exact site matters. A thermal limit is about the line or transformer carrying the current, so it's much the same along that stretch. Voltage drops the farther the load is from the substation, so a voltage limit can read quite differently half a mile down the same feeder.
Load maps are a simpler test than they look. On Central Hudson's, the headroom is the circuit's rating minus last summer's peak on that feeder. It works out exactly for every feeder on the November map. The Joint Utilities say New York's electrification maps assume the thermal limit is the one that binds, and don't model voltage. For a large charger near the end of a long feeder, the storage map's charging layer is worth a look too, because it tests voltage at that section of line. (Charging vs discharging headroom.)
Check the substation line once
Feeder headroom and substation headroom are separate numbers. Central Hudson's load map shows the substation transformer's rating, but not its peak, and the feeder headroom subtracts nothing at the substation. Its storage map shows both. In November, none of the 230 feeders with a charging figure had less room at the substation than on the feeder, so the substation wasn't the tighter limit there. It won't always hold, and it takes a minute to check: subtract the substation's peak from its rating, and if the result is smaller than the feeder's figure, the substation is your limit.
The study leaves out whatever connected after it
Pop-ups often list generation connected since the last study and generation still in the queue. Central Hudson's own guidance says a large figure for generation added since the refresh can mean the real hosting capacity is lower than the map shows. On its storage map, 14 feeders show more than 1 MW connected since the April study, and 30 show more than 1 MW still queued.
For load the gap is wider. The Joint Utilities say the electrification maps don't model queued projects or forecast load growth, and New York's state data portal says its EV layer doesn't account for other planned loads. If any of that queue is batteries, their charging is load on the same feeder.
Most notes are about export
The Notes field is for whatever doesn’t fit a column. On Central Hudson's storage map, 86 of the 101 notes say only "Fault Current Limitation". The other 15, all in one part of the system, say a direct transfer trip is required, and 9 of them add a transmission constraint.
Both are about generation. Fault current and transfer trip matter when a project can push power back onto the line. A site with chargers only isn't affected. A battery that discharges, or a solar canopy over the chargers, may be. A contractor who opens only the load map never sees these notes, because it doesn't have any.
Some of the fine print is a whole view rather than a field. Con Edison's map splits its territory into network and non-network areas. In a network area the map shows availability at an underground transformer, not along a feeder, so a feeder figure from the other view doesn't apply to the site.
When a note names something you don't recognize, ask the utility what it means for your load before you rely on the number.
What to copy into your file
For each feeder near the site:
- substation and feeder name, and the study date for the section nearest the site
- the lowest figure near the site, and which test set it if the map says
- the substation's rating and last year's peak
- generation connected since the study, and in the queue
- the note, word for word, from every map the utility publishes
It takes a few minutes per feeder, and later nobody has to work out which version of the map a quote was based on. (How to check EV charging capacity at a site before you quote.)
If a pop-up near your site says something you can't place, send an address. We'll read the fields for the feeders near it, tell you what has changed since the last study, and what to ask the utility.