How much grid capacity does an electric truck or bus depot need?

Thirty electric trucks on 150 kW chargers add up to 4.5 MW of chargers. On Central Hudson's load capacity map, with figures dated March 31, 2026, 6 of its 217 feeders show that much room in both summer and winter. If the same trucks only have to put back what they used in a day, spread over the night, the depot needs closer to 1.2 MW, and 92 feeders show that much.

Which of those two numbers the utility plans for decides most of the cost and the timeline. Here's how to work out both, and what it takes to get the smaller one studied.

Count the energy, not the chargers

Charger nameplate is the easy number: ports times rating. It's often the number a load letter starts from (load forms and load letters). But a depot only has to replace the energy the vehicles used, in the hours they're parked.

Take the trucks. A short-haul tractor running about 200 miles a day, at about 2 kWh a mile, uses roughly 400 kWh. Thirty of them need about 12 MWh back each night. Over a ten-hour stop, that's 1.2 MW on average, or 40 kW a truck. NREL, working from real short-haul truck schedules, found that depot charging could be met at 100 kW per vehicle or less.

The 150 kW chargers still earn their place. They cover the truck that comes back late or has to turn around at midday. They just don't all need to run at once.

Try it with your own fleet below. The feeder counts are from Central Hudson's map with figures dated March 31, 2026, so read them as March figures; the utility's next refresh will change them.

Try it with your fleet

Feeder counts use Central Hudson's load capacity map, with figures dated March 31, 2026.

Charger rating, per vehicle

All chargers at full power

Average draw while parked

Feeder counts: Central Hudson's 217 feeders with a published figure, on its load capacity map with figures dated March 31, 2026, the version still shown in November 2026. A feeder is counted if both its summer and winter headroom are at least the load. The average assumes charging is spread evenly over the hours parked; a real depot needs some margin above it, and the utility may study the full charger rating unless the draw is capped. A first screen only, not a utility answer.

Bus depots are already close to their real load

School buses carry smaller batteries. NYSERDA's guidebook puts most electric school bus batteries between 120 and 210 kWh, and a Level 2 charger at about 19 kW, enough to refill one in 6 to 11 hours. Forty buses on Level 2 come to about 770 kW, and 113 of Central Hudson's 217 feeders show that much room.

On Level 2 there's little to manage, because the chargers already run at about the rate the buses need. The jump comes with DC. A 60 kW charger at each of the same forty buses is 2.4 MW, which 37 feeders show, and the buses don't drive a mile further.

New York's budget this year moved the zero-emission purchase requirement for school buses from 2027 to 2032, and the full-fleet deadline from 2035 to 2040. That's time to put the request in at the size the routes need.

The map shows the worst hour

Central Hudson's headroom figure is the circuit's rating minus the feeder's peak, once for summer and once for winter (reading the fine print on a utility capacity map). A depot that charges from 9 p.m. to 6 a.m. isn't drawing at that hour, so on most feeders there's more room overnight than the map shows.

The map won't say how much more, and the utility won't assume it. Unless something holds the depot's draw down, a service study can treat every charger as running flat out at the worst hour of the year.

Read the winter column too

Overnight charging in January lines up with heating load, and a cold battery takes more energy to fill. On 44 of Central Hudson's 217 feeders the winter headroom is smaller than the summer figure, and on 11 the summer figure shows room while the winter one shows none. For a depot, use the smaller of the two (reading negative capacity values).

Getting the smaller number studied

Two things have to line up.

Inside the fence, the National Electrical Code lets the service and feeders be sized to the most an energy management system will allow, rather than the sum of the chargers. Set the depot's managed limit at 1.2 MW and the electrical design can be built to that.

The utility then has to plan around the same limit. New York's word for this is a flexible connection: the customer agrees to a cap, either fixed, on a schedule, or moving with grid conditions, and in return can connect sooner or with smaller upgrades. In June the Department of Public Service's staff described these options as inconsistently available across the utilities. So ask early, and in writing, whether the utility will study the depot at its managed limit, and whether it would allow a higher limit at night than during the day.

Ask for the whole fleet, not the first phase

Most fleets electrify in steps. Ten trucks this year and thirty by 2030 are two different requests, and nobody holds the headroom for you in between (why a make-ready quote can go stale). Give the utility the full plan with dates, so the first design leaves room for the rest even if the later upgrades are built later.

Check the incentives before the service request, too. The utilities' Medium- and Heavy-Duty Make-Ready Pilot runs separately from the light-duty program and was still taking applications in November. It can cover up to 90% of the utility-side cost, and it starts with the utility's fleet assessment. Customer-side help depends on location: a private depot outside a disadvantaged community gets the utility-side share only.

What to bring to the first call

  • Vehicles by phase, with dates
  • The energy each vehicle needs back on a normal day, and the hours it's parked
  • Charger count and rating
  • The managed limit you'd commit to, and whether it could be higher overnight
  • The feeder the map shows at the site, its summer and winter headroom, and the date on those figures

For the rest of the request, see what goes into a first utility inquiry.