Why an EV make-ready quote can go stale before the client signs
On March 23, 2026, New York's Public Service Commission told the state's investor-owned utilities to stop taking new Level 2 applications to the EV Make-Ready Program and to pause new DC fast-charger applications. Level 2 applications closed on April 22. Eight months later, the fast-charger side is still paused. A contractor who priced a Level 2 job in March with the make-ready incentive netted out had a quote that no longer added up by the time the client was ready to sign.
The incentive is one of several things in a make-ready quote that can change while it waits. Here are the ones that move most often, and how to write a quote that survives them.
Most of New York's make-ready money is on hold
New York's light-duty Make-Ready Program covered part of the utility-side and customer-side cost of chargers. Under the March order:
- Level 2 applications closed on April 22, 2026, and NYSEG says it doesn't expect to reopen them. Complete applications filed before the deadline go ahead.
- The DC fast-charger part is paused. In a June 12 clarification, the Commission said it reopens statewide only after every utility shows at least 90% data-reporting compliance for its incentivized fast chargers. There is no date.
- National Grid stopped accepting Level 2 and fast-charger make-ready applications on April 3.
- The medium- and heavy-duty pilot is still open for fleets, first come, first served, until each utility's funding is allocated.
Federal money moved too. The Section 30C credit for charging equipment isn't allowed for property placed in service after June 30, 2026. In New Jersey, the utilities' light-duty EV programs were approved for a fixed number of years. In May 2026 the Board of Public Utilities told each utility to petition for an extension of up to a year, with no new budget.
None of this shows up on a capacity map. Before a quote goes out, check the program's own page that week, and write down its status and the date you checked.
The map you priced against may be gone
Utilities recalculate their load maps on their own schedules, often once a year. (How often utilities refresh their capacity maps.) In April 2026, Central Hudson replaced figures dated May 2025 with figures dated March 31, 2026. Of the 217 feeders on both versions, 129 showed at least 1.2 MW of summer headroom in the old figures, enough for a depot of eight 150 kW chargers. In the new figures, 37 of them no longer do, while 11 others rose past that line. And 27 feeders that showed some headroom now show none. (What changed in April.)
A quote written against the old map was priced on a service the utility might no longer offer without an upgrade. (How to check EV charging capacity at a site before you quote.)
Nobody holds the headroom for you
A load map is a snapshot. It doesn't hold capacity for anyone. New York's state data portal says its EV load capacity layer doesn't account for other planned loads. National Grid's New York service guide warns that load commitments on its system change, and that its first answer to a request can change with them.
So if a warehouse two streets away applies for a large service upgrade while your client is deciding, the headroom you priced against can go to them. You can't see that coming on the map. Ask the utility at what point in its process capacity is set aside for a request, and tell the client how far the job has to get before it counts.
The utility hasn't seen the load yet
The map is a feeder-level screen. The utility's service review looks at the transformer, the secondary lines and the service itself, and that's where the scope of the utility-side work gets set. (Load form and load letter.) If the review finds the local transformer too small, the job now includes a utility upgrade. Depending on the tariff, the client may pay part of it. (Who pays for the line.) A quote written before the utility has seen the load is a guess at that scope.
Transformers are still about a year out
Lead times are still long. The US Department of Energy says distribution transformer lead times went from three to six months in 2019 to 12 to 30 months in 2023, its latest data. In September 2026, a national contractor was reporting 40 to 65 weeks for pad-mount transformers and 52 to 80 weeks for medium-voltage switchgear, according to Foley & Lardner. If a utility transformer has to be replaced too, its lead time counts against the schedule as well.
A price held for 30 days doesn't help much if the gear behind it is a year out. A delivery date that slips past an incentive deadline can cost the client more than the gear.
What to put in the quote
Most of these can't be controlled, but they can be dated. A short assumptions block makes it clear which version of the world the price is based on:
Based on {utility}'s published load capacity for feeder {name}, dated {date}. Incentive: {program}, status as of {date checked}; price shown with and without it. No federal tax credit assumed. Equipment lead times as quoted by suppliers on {date}. Subject to the utility's service review; any utility-side upgrade it requires is priced separately.
Then re-check before the client signs if any of these happen: the map refreshes (several New York utilities refresh in spring), the program posts a notice, or more than a few weeks pass.
If you're holding quotes for sites in New York or New Jersey, send an address. We'll tell you what the published map showed when you quoted, whether it has changed since, and what to ask the utility.