Synthetic example. The site, utility, feeders and figures are made up to show the format. They are not real utility data.

Site check: 4 × 150 kW chargers at 100 Example Road

The question

Can the nearby feeder take about 600 kW of new charging load, and has its published capacity changed since the contractor's January quote?

The answer

Probably yes for phase 1, with less room than in January. The published load-serving headroom on Example Feeder 12 fell from 2.4 MW to 0.9 MW when Example Utility refreshed its map on April 15. 600 kW still fits under the new figure; a second phase of the same size would not.

Synthetic chart: published summer load-serving headroom on Example Feeder 12, weekly captures from February 25 to November 18, 2026 The figure is 2.4 MW in every weekly capture from February 25 to April 8, then 0.9 MW in every capture from April 15 to November 18. A dashed line marks the planned load of 0.6 MW, below the new figure. 3 MW210 Your planned load (600 kW) 2.4 MW 0.9 MW Feb 25Apr 15Jul 1Sep 2Nov 18
Published summer load-serving headroom, Example Feeder 12 (synthetic). Source date changed from May 2025 to March 2026 on April 15.

Nearby feeders

Nearby feeders (synthetic)
Feeder (synthetic)Published headroomChange
Example Feeder 120.9 MWChanged Apr 15 (was 2.4)
Example Feeder 143.1 MWUnchanged since Feb 25
Example Feeder 9–Dropped off the map Apr 15

What this metric means

Load-serving headroom is the utility's estimate of how much new load a feeder can take before upgrades. It is not a hosting-capacity figure for solar or storage, and it doesn't cover the transformer or service at your site.

Ask the utility

Can Example Feeder 12 serve an additional 600 kW at 100 Example Road in 2027, and does the April 15 figure change the service or line-extension work you'd expect?