Site check: 4 × 150 kW chargers at 100 Example Road
The question
Can the nearby feeder take about 600 kW of new charging load, and has its published capacity changed since the contractor's January quote?
The answer
Probably yes for phase 1, with less room than in January. The published load-serving headroom on Example Feeder 12 fell from 2.4 MW to 0.9 MW when Example Utility refreshed its map on April 15. 600 kW still fits under the new figure; a second phase of the same size would not.
Nearby feeders
| Feeder (synthetic) | Published headroom | Change |
|---|---|---|
| Example Feeder 12 | 0.9 MW | Changed Apr 15 (was 2.4) |
| Example Feeder 14 | 3.1 MW | Unchanged since Feb 25 |
| Example Feeder 9 | – | Dropped off the map Apr 15 |
What this metric means
Load-serving headroom is the utility's estimate of how much new load a feeder can take before upgrades. It is not a hosting-capacity figure for solar or storage, and it doesn't cover the transformer or service at your site.
Ask the utility
Can Example Feeder 12 serve an additional 600 kW at 100 Example Road in 2027, and does the April 15 figure change the service or line-extension work you'd expect?