Siting a plant in New York or New Jersey: which grid are you asking about?

At the end of 2025, New York's grid operator had 48 large load projects in its interconnection queue, asking for about 12 GW between them. In 2022 there were six, totaling 1 GW. Most are data centers, but the same studies apply to a battery plant, a semiconductor fab or a large food factory. If your company is choosing a US site in New York or New Jersey, start with the size of your load, not the capacity map. The size decides which part of the grid you connect to, who studies the request, and how long it takes.

Two grids, and the maps show one

Utilities run two systems. The distribution system is the lower-voltage feeders, often 13 kV, that serve offices, warehouses, labs and most factories. The transmission system runs at 69 kV and above and ties substations to power plants and to each other.

The capacity maps that New York and New Jersey utilities publish cover the distribution side: feeders and the substations that serve them. (Hosting capacity maps vs distribution load serving capacity maps.) They don't tell you how much load the transmission system can take at a given point.

The line between the two is set by each utility and grid operator, but the published thresholds are close:

  • PSE&G tells data center customers to expect service at 69 kV or above, and to set aside about 2.5 acres for substation equipment at 69 to 230 kV.
  • In New York, National Grid sends any new load, or load increase, above 10 MW at 115 kV or higher, or above 80 MW at lower voltage, through a study by the state grid operator, NYISO.
  • PJM, which runs the grid in New Jersey, drew its large load line in January 2026 at 50 MW at a single point of interconnection.

Roughly: a warehouse, a lab or a plant of a few megawatts is a distribution question, and the maps are a fair first screen. A plant in the tens of megawatts usually needs its own substation fed from transmission, and the maps can tell you little more than which substations are nearby. In between, ask the utility early.

What one feeder can hold

Central Hudson's current load map, with figures dated March 31, 2026, shows summer headroom for 217 feeders. The median feeder shows about 1.1 MW, and 47 show none. Only 3 show 10 MW or more, and the largest figure is about 14.5 MW. Even a 15 MW plant fits on none of them.

Spreading a large load across several feeders is possible, but at that point the utility is designing a dedicated supply, and the study is about the substation and the lines behind it. If your plant can't stop for an outage, ask about a second feed at the same time. (Redundant feed.)

What the process looks like in New York

National Grid's March 2026 guide lays out the path for large loads on its New York transmission system:

  1. Early engagement: 1 to 3 months, up to $30,000 depending on what you ask for. You get a high-level, non-binding view of the load's impact.
  2. NYISO system impact study: 6 to 12 months, with a $150,000 deposit.
  3. Facility study by the utility: 9 to 15 months, $200,000 to $500,000. It gives an upgrade scope, a cost estimate and a high-level schedule.
  4. Engineering, procurement and construction: 2 years or more, depending on the upgrades. To start engineering, you pay about 10% of the project cost up front.

Laid end to end, those ranges come to more than three years from the first call to power. National Grid also says nothing in the first three steps reserves capacity for you.

What it looks like in New Jersey

PSE&G starts with a feasibility study of 12 to 16 weeks. It tells you the voltage, roughly how much capacity is available, and the timing and rough cost of the utility's work. PSE&G puts the whole build at two to four years.

Large requests also show up in public. When a customer asks PSE&G for a new transmission connection, the utility presents the need at PJM's planning committees, usually without naming the customer. In February 2026, for example, it described a new customer asking for a 230 kV connection for 120 MW in the Hamilton area. Those presentations are a good way to see which new substations and lines are already planned near a site.

Check which utility serves the address. New Jersey has four investor-owned electric utilities, and a town name doesn't always tell you which one serves a parcel. Look the address up on the state's territory map or ask the utility.

The rules are being rewritten

In June 2026, federal regulators (FERC) told every US grid operator to explain or reform how it connects loads over 50 MW. NYISO and PJM filed their answers on November 16, 2026:

  • NYISO proposes a study path of 18 to 24 months. A load that strains the state's supply of capacity by more than 25 MW either brings a new supply resource of its own or accepts non-firm service on that part, which can be cut when prices run high.
  • PJM proposes to study generation and large loads together in a single 12-month cycle.

Neither has been accepted yet, and both are aimed at early 2027. The states are moving too. New York's Public Service Commission opened a proceeding on February 12, 2026 on how large loads connect and who pays for the upgrades. New Jersey's Data Center Fair Share Act, signed in July 2026, creates a separate rate class for large data centers; it doesn't cover factories.

If you file in 2027, ask which version of the rules your request will be studied under.

Questions for the first call

  • What voltage would serve a load this size here, and from which substation?
  • Which study applies, how long does it take, and what does it cost?
  • Does anything reserve capacity for us, and at what step?
  • Does the request go to NYISO or PJM, and under which rules?
  • Can we get a second feed, and from where?
  • Are upgrades already planned nearby, and who pays for the ones we trigger?

Where the maps still help

For a smaller site, the maps are a quick screen before you call. For a large one, they show which substations are close, how loaded they are, and how stale the figures might be. (How often utilities refresh their capacity maps.) Either way, they're screening values, not a commitment from the utility.

If you're comparing sites in New York or New Jersey, send an address. We'll tell you which utility serves it, what its published maps show nearby, and whether your load size makes it a transmission question.